Weekly
Mill performance
[posted 24 Nov 2011,1130]
The
four mills crushed a low of 60,000 tonnes of cane in the week-ended 21
November, bringing total cane crushed this season to 1.8 million tonnes.
Individual mill figures are as follows:
|
MILL |
WEEKLYCRUSH (tonnes) |
SEASON TO DATE
(tonnes) |
|
LAUTOKA |
21,447 |
541,961 |
|
RARAWAI |
17,553 |
556,119 |
|
LABASA
|
13,575 |
498,729 |
|
PENANG |
7395 |
202,578 |
|
TOTAL
|
59,970 |
1,799,387 |
| |
|
|
|
The
Lautoka Mill was out of action for 72 hrs (3 days) because of mechanical
breakdowns and staggered cane supply.
The
Raiwai and Labasa Mills were also plagued by mechanical failures resulting
in very slow crush rates. Penang Mill is due to shut down at the end of the
week after crushing around 210,000 tonnes.
TCTS is
averaging at between 12.5 -13.0 and is likely to deteriorate with almost
100% burnt cane now being delivered to the mills.
S.Lal |